How do you find the real bottleneck in a manufacturer with six factories?
Industry: Manufacturing
The short answer
Welding found as the true bottleneck. Inventory prediction added so purchasing never stalled the line.
What the problem was and what was done
Heavy production machinery for lighting poles and towers fitted with sensors and integrated with Oracle E-Business Suite, tracking every pole by order, stage, machine, scrap and time across six factories. The schedule was reordered to cut multi-hour changeovers.